Section N/A. What happened:
No kickoff or handover to the Well Management team.

What Was Planned

Well Expertise should request a handover/kick-off meeting by DNO. It is very important to get expectations, project information, and processes to ensure efficient planning and alignment in the team.

What Actions Are Required

WE project manager will request kick off meeting from Client for next project where all expectations and plans are presented. HSEQ systems and objectives, C&P – templates and procedures, Drilling – plans and way forward, G&G – prospect and objectives.